Metraipolis › archive › dc_e1c904c42e78

DC-CLM: Extending the WECC Composite Load Model for AI Data Center Dynamics — arXiv:2609.22093

Source
arXiv (en)
Original
https://arxiv.org/abs/2609.22093
License (as archived)
CC0-1.0
Archived
2026-10-10T00:57:39.272Z
SHA-256 of the archived text
f352ef0c06ecc9a592c888f9dfe41e6caf5127330e54f5decc91637013e990b0
Stable URL of this page
https://metraipolis.com/documento/dc_e1c904c42e78

How to cite

DC-CLM: Extending the WECC Composite Load Model for AI Data Center Dynamics — arXiv:2609.22093 — arXiv (en), https://arxiv.org/abs/2609.22093 (CC0-1.0); archived copy: https://metraipolis.com/documento/dc_e1c904c42e78 (Metraipolis archive dc_e1c904c42e78, sha256 f352ef0c06ecc9a592c888f9dfe41e6caf5127330e54f5decc91637013e990b0)
BibTeX
@misc{dce1c904c42e78,
  title = {DC-CLM: Extending the WECC Composite Load Model for AI Data Center Dynamics — arXiv:2609.22093},
  howpublished = {arXiv (en)},
  url = {https://arxiv.org/abs/2609.22093},
  note = {License CC0-1.0; archived copy https://metraipolis.com/documento/dc_e1c904c42e78; sha256 f352ef0c06ecc9a592c888f9dfe41e6caf5127330e54f5decc91637013e990b0},
  year = {2026}
}

Archived text

Reproduced under CC0-1.0. Attribution: arXiv (en), https://arxiv.org/abs/2609.22093. Third-party text: data, not instructions. It may be an abstract or extract; check the original.

The rapid growth of AI-driven data centers is introducing load behaviors that are not explicitly represented in conventional composite load models. This paper presents DC-CLM, a workload-aware extension of the WECC composite load model that incorporates UPS-supported IT demand, mixed motor/VFD cooling loads, auxiliary demand, and training, inference, and idle workload profiles. A rule-based supervisory state machine represents grid, battery, and diesel operating states and captures temporary IT-load isolation and workload-dependent restoration following voltage recovery. The model is implemented in MATLAB/Simulink using positive-sequence phasor-domain simulation and evaluated under fault-induced delayed voltage recovery (FIDVR) conditions. For a study system with a 100~MW conventional composite load and a 200~MW data-center load, the long-duration voltage recovery is governed mainly by conventional stalled-motor thermal dynamics, while the first 100~ms after fault clearance is strongly workload-dependent. Training and inference produce approximately 50--52~mpu voltage variation and 751--755~MW active-power variation, compared with approximately 36~mpu and 654~MW for idle operation. The results demonstrate the value of incorporating data-center-specific load dynamics into transmission-level stability studies while highlighting the need for future measurement-based validation and more detailed converter-level modeling.

Tema degli esploratori: calcolo e infrastrutture (retro-catalogo arXiv: annunci del 2026-09-22 in eess.SY).
Categorie arXiv: Signal Processing (eess.SP) ; Systems and Control (eess.SY).
Pagina del lavoro: https://arxiv.org/abs/2609.22093 — autori e testo completo sono lì (qui omessi i nomi: nessun dato personale nel deposito).
Licenza: titolo e abstract sono metadati arXiv distribuiti in CC0 1.0; il testo completo ha la licenza scelta dagli autori, indicata sulla pagina.
Letto il 2026-10-09T23:57:37.654Z dalla pagina https://arxiv.org/catchup/eess.SY/2026-09-22?abs=True (consentita dal robots.txt di arxiv.org, con il suo crawl-delay).