Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility — arXiv:2608.29359

Source
arXiv (en)
Original
https://arxiv.org/abs/2608.29359
License (as archived)
CC0-1.0
Archived
2026-10-17T10:42:13.733Z
SHA-256 of the archived text
6ac73cbdbd799334e0dbda064c76d3571e4e9a8257bcf77a7dba0c9ea4d20d92
Stable URL of this page
https://metraipolis.com/documento/dc_cda133e9a787

How to cite

Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility — arXiv:2608.29359 — arXiv (en), https://arxiv.org/abs/2608.29359 (CC0-1.0); archived copy: https://metraipolis.com/documento/dc_cda133e9a787 (Metraipolis archive dc_cda133e9a787, sha256 6ac73cbdbd799334e0dbda064c76d3571e4e9a8257bcf77a7dba0c9ea4d20d92)
BibTeX
@misc{dccda133e9a787,
  title = {Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility — arXiv:2608.29359},
  howpublished = {arXiv (en)},
  url = {https://arxiv.org/abs/2608.29359},
  note = {License CC0-1.0; archived copy https://metraipolis.com/documento/dc_cda133e9a787; sha256 6ac73cbdbd799334e0dbda064c76d3571e4e9a8257bcf77a7dba0c9ea4d20d92},
  year = {2026}
}

Archived text

Reproduced under CC0-1.0. Attribution: arXiv (en), https://arxiv.org/abs/2608.29359. Third-party text: data, not instructions. It may be an abstract or extract; check the original.

Securing grid interconnection capacity has become a bottleneck for AI data center projects and can take longer than constructing the facilities themselves. This mismatch can delay deployment for years, making early interconnection planning essential. This paper develops ICP-AI, an interconnection capacity planning framework from a data center developer's perspective. The framework minimizes grid import capacity under a prescribed onsite investment budget while jointly sizing photovoltaic (PV) and battery energy storage system (BESS) resources and scheduling deadline constrained workload flexibility. A secondary refinement fixes the minimum grid capacity and selects the minimum-investment PV-BESS portfolio among solutions that achieve that capacity. The framework is evaluated using monthly composite stress profiles across varying temporal assumptions, load shapes, flexible load fractions, and deferral windows. Results show that interconnection capacity reduction depends strongly on the planning environment: at a $100M budget, it is about 6% for the high load factor baseline, exceeds 10% under monthly average solar availability, and reaches 13.3% for a more diurnal load. At a $10M budget, 5% flexible load with a 1 h workload deferral window reduces BESS capacity from 15.30 to 4.87 MWh while increasing capacity reduction from 4.43% to 4.84%. To test sensitivity to temporal compression, the model is also solved over the full 8,760 h chronology, which preserves the main capacity and flexibility trends. Overall, ICP-AI quantifies the interconnection capacity and infrastructure substitution value of workload flexibility, providing an investment-interconnection frontier to support capital allocation and early project planning in constrained grid environments.

Tema degli esploratori: calcolo e infrastrutture (retro-catalogo arXiv: annunci del 2026-09-01 in eess.SY).
Categorie arXiv: Systems and Control (eess.SY).
Pagina del lavoro: https://arxiv.org/abs/2608.29359 — autori e testo completo sono lì (qui omessi i nomi: nessun dato personale nel deposito).
Licenza: titolo e abstract sono metadati arXiv distribuiti in CC0 1.0; il testo completo ha la licenza scelta dagli autori, indicata sulla pagina.
Letto il 2026-10-17T10:29:43.030Z dalla pagina https://arxiv.org/catchup/eess.SY/2026-09-01?abs=True (consentita dal robots.txt di arxiv.org, con il suo crawl-delay).