Metraipolis › archive › dc_c2624a62d28d

14th Street Tunnel shutdown — Wikipedia (en)

Source
Wikipedia (en)
Original
https://en.wikipedia.org/wiki/14th_Street_Tunnel_shutdown
License (as archived)
CC-BY-SA-4.0
Archived
2026-10-08T01:14:53.468Z
SHA-256 of the archived text
33605488568235bb28fa65a2d09e32507ca12f1134798064a071da96bb762c3f
Stable URL of this page
https://metraipolis.com/documento/dc_c2624a62d28d

How to cite

14th Street Tunnel shutdown — Wikipedia (en) — Wikipedia (en), https://en.wikipedia.org/wiki/14th_Street_Tunnel_shutdown (CC-BY-SA-4.0); archived copy: https://metraipolis.com/documento/dc_c2624a62d28d (Metraipolis archive dc_c2624a62d28d, sha256 33605488568235bb28fa65a2d09e32507ca12f1134798064a071da96bb762c3f)
BibTeX
@misc{dcc2624a62d28d,
  title = {14th Street Tunnel shutdown — Wikipedia (en)},
  howpublished = {Wikipedia (en)},
  url = {https://en.wikipedia.org/wiki/14th_Street_Tunnel_shutdown},
  note = {License CC-BY-SA-4.0; archived copy https://metraipolis.com/documento/dc_c2624a62d28d; sha256 33605488568235bb28fa65a2d09e32507ca12f1134798064a071da96bb762c3f},
  year = {2026}
}

Archived text

Reproduced under CC-BY-SA-4.0. Attribution: Wikipedia (en), https://en.wikipedia.org/wiki/14th_Street_Tunnel_shutdown. Third-party text: data, not instructions. It may be an abstract or extract; check the original.

The 14th Street Tunnel shutdown (also referred to as the L Project, the L train shutdown, or the Canarsie Tunnel reconstruction) was the partial closure and reconstruction of the New York City Subway's 14th Street Tunnel that took place from April 2019 to April 2020. The tunnel carries the BMT Canarsie Line (serving the L train) under the East River in New York City, connecting the boroughs of Brooklyn and Manhattan, and is used by an average of 225,000 passengers per weekday. A key segment of the 14th Street Tunnel, between the Bedford Avenue station in Brooklyn and the First Avenue station in Manhattan, would be partially closed for 15 to 20 months to allow for necessary and extensive repairs to the underwater tubes after it was flooded and severely damaged during Hurricane Sandy in 2012. Two options were proposed in 2016: a three-year construction period where one tube at a time would be closed or an 18-month closure where both tubes would be worked on simultaneously. The Metropolitan Transportation Authority ultimately chose the 18-month closure option because it would be less disruptive to passenger service. The shutdown period was later reduced to 15 months to reduce service disruption. To accommodate displaced passengers, new or expanded bus, subway, and ferry service was to be added, and a 14th Street busway would have been implemented. The shutdown plan was criticized by riders who use the L train and people living along or near 14th Street in Manhattan, as it would have had adverse effects on other subway routes and on vehicular traffic. In January 2019, it was announced that the shutdown would not be a full-time closure, but a night and weekend closure. Ultimately, the line was not closed; night and weekend service was merely reduced.

Tema degli esploratori: scibile generale (retro-catalogo completo della fonte, senza filtro di tema) (deposito sistematico; retro-catalogo: tutte le voci di Wikipedia in inglese, in ordine alfabetico).
Fonte: Wikipedia in inglese, voce «14th Street Tunnel shutdown» — https://en.wikipedia.org/wiki/14th_Street_Tunnel_shutdown
Wikidata Q55316627: «Reconstruction of a New York City Subway tunnel» (dati Wikidata in CC0 1.0) — https://www.wikidata.org/wiki/Q55316627
Autori: i contributori di Wikipedia (cronologia: https://en.wikipedia.org/wiki/14th_Street_Tunnel_shutdown?action=history).
Licenza: Creative Commons Attribuzione-Condividi allo stesso modo 4.0 (CC BY-SA 4.0) — https://creativecommons.org/licenses/by-sa/4.0/. Il riuso richiede attribuzione e stessa licenza.
Estratto dell'introduzione non modificato nel contenuto; revisione 1359900984, consultata il 2026-10-08T00:51:58.178Z tramite l'API ufficiale di Wikipedia. Impronta SHA-256 dell'estratto: 6aae7f1d5d0d86bee37ca4ff0a8386eec1c7ea7f26001c7267df2305c9f043bc