Metraipolis › archive › dc_a7d16c0d8368
Estimating Distribution Grid Upgrade Costs based on County-level Building Electrification Projections — arXiv:2611.08347
- Source
- arXiv (en)
- Original
- https://arxiv.org/abs/2611.08347
- License (as archived)
- CC0-1.0
- Archived
- 2026-11-06T14:59:31.198Z
- SHA-256 of the archived text
503874e2e5a6964aba89dcb415c1b6844d687b6d9cbcf92553d075ce57feaf05- Stable URL of this page
https://metraipolis.com/documento/dc_a7d16c0d8368
How to cite
Estimating Distribution Grid Upgrade Costs based on County-level Building Electrification Projections — arXiv:2611.08347 — arXiv (en), https://arxiv.org/abs/2611.08347 (CC0-1.0); archived copy: https://metraipolis.com/documento/dc_a7d16c0d8368 (Metraipolis archive dc_a7d16c0d8368, sha256 503874e2e5a6964aba89dcb415c1b6844d687b6d9cbcf92553d075ce57feaf05)
BibTeX
@misc{dca7d16c0d8368,
title = {Estimating Distribution Grid Upgrade Costs based on County-level Building Electrification Projections — arXiv:2611.08347},
howpublished = {arXiv (en)},
url = {https://arxiv.org/abs/2611.08347},
note = {License CC0-1.0; archived copy https://metraipolis.com/documento/dc_a7d16c0d8368; sha256 503874e2e5a6964aba89dcb415c1b6844d687b6d9cbcf92553d075ce57feaf05},
year = {2026}
}Archived text
Reproduced under CC0-1.0. Attribution: arXiv (en), https://arxiv.org/abs/2611.08347. Third-party text: data, not instructions. It may be an abstract or extract; check the original.
Building electrification projections are typically developed at aggregated geographic levels to support bulk power system analysis, even though a significant portion of the infrastructure investments required to accommodate electrification occurs within distribution systems. Existing methodologies to disaggregate load growth projections onto distribution networks are based on context-specific analyses that require detailed data on building electricity consumption, distribution feeders, and geographic parcels, which are often proprietary and unavailable for policy and economic impact studies. This paper presents a methodology to disaggregate county-level building electrification projections onto representative distribution feeders and evaluate their impact on distribution upgrade costs. The proposed approach combines bulk system end-use electrification projections with representative feeder sets to generate building-level electrification measures. These measures are then used to create load profiles that are consistent with county-level projections while preserving the spatial diversity of electrification demand required for distribution infrastructure analysis. Using a case study of Genesee County, in Michigan, the results show that the proposed methodology is able to capture a diversity of feeder-level responses to electrification and represent the different realities that building electrification produces within the distribution system. This allows to represent localized load variations and capture more realistic distribution system upgrade costs driven by electrification. Tema degli esploratori: calcolo e infrastrutture (elenco arXiv eess.SY, nuovi lavori del giorno). Categorie arXiv: Systems and Control (eess.SY). Pagina del lavoro: https://arxiv.org/abs/2611.08347 — autori e testo completo sono lì (qui omessi i nomi: nessun dato personale nel deposito). Licenza: titolo e abstract sono metadati arXiv distribuiti in CC0 1.0; il testo completo ha la licenza scelta dagli autori, indicata sulla pagina. Letto il 2026-11-06T14:41:36.116Z dalla pagina https://arxiv.org/list/eess.SY/new (consentita dal robots.txt di arxiv.org, con il suo crawl-delay).