Prosumer Synchronisation Risk: Impacts of Time-Varying Tariffs on Distribution Network Expansion — arXiv:2609.02174

Source
arXiv (en)
Original
https://arxiv.org/abs/2609.02174
License (as archived)
CC0-1.0
Archived
2026-10-17T06:27:55.926Z
SHA-256 of the archived text
038f1e0022f9fa4c13a2d8578bfdabe4190bb12d9cc50c7b52493a588f31fa23
Stable URL of this page
https://metraipolis.com/documento/dc_8a19401a5856

How to cite

Prosumer Synchronisation Risk: Impacts of Time-Varying Tariffs on Distribution Network Expansion — arXiv:2609.02174 — arXiv (en), https://arxiv.org/abs/2609.02174 (CC0-1.0); archived copy: https://metraipolis.com/documento/dc_8a19401a5856 (Metraipolis archive dc_8a19401a5856, sha256 038f1e0022f9fa4c13a2d8578bfdabe4190bb12d9cc50c7b52493a588f31fa23)
BibTeX
@misc{dc8a19401a5856,
  title = {Prosumer Synchronisation Risk: Impacts of Time-Varying Tariffs on Distribution Network Expansion — arXiv:2609.02174},
  howpublished = {arXiv (en)},
  url = {https://arxiv.org/abs/2609.02174},
  note = {License CC0-1.0; archived copy https://metraipolis.com/documento/dc_8a19401a5856; sha256 038f1e0022f9fa4c13a2d8578bfdabe4190bb12d9cc50c7b52493a588f31fa23},
  year = {2026}
}

Archived text

Reproduced under CC0-1.0. Attribution: arXiv (en), https://arxiv.org/abs/2609.02174. Third-party text: data, not instructions. It may be an abstract or extract; check the original.

The rapid deployment of distributed energy resources, including heat pumps, electric vehicles, photovoltaics, and battery storage, is reshaping the operation of low-voltage networks. While distribution system operators often aim to develop time-varying tariffs to incentivise network-friendly behaviour and defer reinforcements, they risk triggering prosumer synchronisation. As prosumers follow price signals, their behaviour may synchronise, avoiding existing load peaks while creating undesirable peaks at other times. This paper quantifies the impact on low-voltage network reinforcement needs when shifting from flat tariffs to two time-varying tariffs: Time-of-Use and Real-Time Pricing. Applying a mixed-integer linear model across 471 low-voltage reference networks in Switzerland, we evaluate expansion requirements under projections of distributed energy resource deployment for 2050. In the model, prosumers operate their distributed energy resources in accordance with their subscribed electricity tariff to minimise costs, and the distribution system operator subsequently optimises reinforcements. Our results demonstrate that while adopting time-varying tariffs can reduce reinforcement investment costs by more than 50%, high adoption rates can reverse this declining trend. Specifically, once prosumer adoption exceeds the optimal thresholds of 50% for Time-of-Use and 40% for Real-Time Pricing, reinforcement needs increase by 39% and 134%, respectively, for an additional 20% of tariff adoption.

Tema degli esploratori: calcolo e infrastrutture (retro-catalogo arXiv: annunci del 2026-09-03 in eess.SY).
Categorie arXiv: Systems and Control (eess.SY).
Pagina del lavoro: https://arxiv.org/abs/2609.02174 — autori e testo completo sono lì (qui omessi i nomi: nessun dato personale nel deposito).
Licenza: titolo e abstract sono metadati arXiv distribuiti in CC0 1.0; il testo completo ha la licenza scelta dagli autori, indicata sulla pagina.
Letto il 2026-10-17T06:13:51.279Z dalla pagina https://arxiv.org/catchup/eess.SY/2026-09-03?abs=True (consentita dal robots.txt di arxiv.org, con il suo crawl-delay).