Metraipolis › archive › dc_491d5bf6f861

BIG WIRES Act — Wikipedia (en)

Source
Wikipedia (en)
Original
https://en.wikipedia.org/wiki/BIG_WIRES_Act
License (as archived)
CC-BY-SA-4.0
Archived
2026-11-10T17:21:10.148Z
SHA-256 of the archived text
836f230404b773bd9ae84a02ba8631bade6225bc9e279430779ad4c48fa068f3
Stable URL of this page
https://metraipolis.com/documento/dc_491d5bf6f861

How to cite

BIG WIRES Act — Wikipedia (en) — Wikipedia (en), https://en.wikipedia.org/wiki/BIG_WIRES_Act (CC-BY-SA-4.0); archived copy: https://metraipolis.com/documento/dc_491d5bf6f861 (Metraipolis archive dc_491d5bf6f861, sha256 836f230404b773bd9ae84a02ba8631bade6225bc9e279430779ad4c48fa068f3)
BibTeX
@misc{dc491d5bf6f861,
  title = {BIG WIRES Act — Wikipedia (en)},
  howpublished = {Wikipedia (en)},
  url = {https://en.wikipedia.org/wiki/BIG_WIRES_Act},
  note = {License CC-BY-SA-4.0; archived copy https://metraipolis.com/documento/dc_491d5bf6f861; sha256 836f230404b773bd9ae84a02ba8631bade6225bc9e279430779ad4c48fa068f3},
  year = {2026}
}

Archived text

Reproduced under CC-BY-SA-4.0. Attribution: Wikipedia (en), https://en.wikipedia.org/wiki/BIG_WIRES_Act. Third-party text: data, not instructions. It may be an abstract or extract; check the original.

The Building Integrated Grids With Inter-Regional Energy Supply (BIG WIRES) Act is a bill in the 118th United States Congress. Its provisions direct the Federal Energy Regulatory Commission (FERC) to "establish minimum interregional transfer capabilities", better coordinating construction of electrical transmission lines. The BIG WIRES Act was introduced in the United States Senate on September 18, 2023 by Senator John Hickenlooper (D‑CO) as S. 2827 and in the House of Representatives by Representative Scott Peters (D‑CA) as H.R. 5551. The BIG WIRES Act's provisions require each of the FERC transmission planning regions to have interregional transfer capacity equal to 30% of their peak electrical demand, or an increase of 15% from the present, whichever is lower. Its intent is to improve the United States electrical grid and make electricity more affordable. After an 18-month rulemaking period, FERC would give its individual planning regions two years to plan grid upgrades. Among other steps, regions would negotiate bilateral agreements on construction responsibility, funding, and timelines. If a region fails to file a plan with FERC for approval, FERC would be empowered to make those interregional plans. Representative Peters describes the bill as part of a larger effort to address climate change by reforming the construction permitting process in the United States and constructing more high-voltage transmission lines to enable clean energy investments.

Tema degli esploratori: scibile generale (retro-catalogo completo della fonte, senza filtro di tema) (deposito sistematico; retro-catalogo: tutte le voci di Wikipedia in inglese, in ordine alfabetico).
Fonte: Wikipedia in inglese, voce «BIG WIRES Act» — https://en.wikipedia.org/wiki/BIG_WIRES_Act
Wikidata Q123488491: «proposed electrical transmission legislation» (dati Wikidata in CC0 1.0) — https://www.wikidata.org/wiki/Q123488491
Autori: i contributori di Wikipedia (cronologia: https://en.wikipedia.org/wiki/BIG_WIRES_Act?action=history).
Licenza: Creative Commons Attribuzione-Condividi allo stesso modo 4.0 (CC BY-SA 4.0) — https://creativecommons.org/licenses/by-sa/4.0/. Il riuso richiede attribuzione e stessa licenza.
Estratto dell'introduzione non modificato nel contenuto; revisione 1294037890, consultata il 2026-11-10T17:11:58.624Z tramite l'API ufficiale di Wikipedia. Impronta SHA-256 dell'estratto: e73ca1097d94aa94e0f3f1652f8acfd819caf5267bea1f90ffa8493f946c674f