Metraipolis › archive › dc_4632926f124a
BK Tooling v Scope Precision Engineering — Wikipedia (en)
- Source
- Wikipedia (en)
- Original
- https://en.wikipedia.org/wiki/BK_Tooling_v_Scope_Precision_Engineering
- License (as archived)
- CC-BY-SA-4.0
- Archived
- 2026-11-10T17:24:15.225Z
- SHA-256 of the archived text
ccb8d300a53134e93d5221cd99212b7babdf558f21ae030a5566f30d17cd7f71- Stable URL of this page
https://metraipolis.com/documento/dc_4632926f124a
How to cite
BK Tooling v Scope Precision Engineering — Wikipedia (en) — Wikipedia (en), https://en.wikipedia.org/wiki/BK_Tooling_v_Scope_Precision_Engineering (CC-BY-SA-4.0); archived copy: https://metraipolis.com/documento/dc_4632926f124a (Metraipolis archive dc_4632926f124a, sha256 ccb8d300a53134e93d5221cd99212b7babdf558f21ae030a5566f30d17cd7f71)
BibTeX
@misc{dc4632926f124a,
title = {BK Tooling v Scope Precision Engineering — Wikipedia (en)},
howpublished = {Wikipedia (en)},
url = {https://en.wikipedia.org/wiki/BK_Tooling_v_Scope_Precision_Engineering},
note = {License CC-BY-SA-4.0; archived copy https://metraipolis.com/documento/dc_4632926f124a; sha256 ccb8d300a53134e93d5221cd99212b7babdf558f21ae030a5566f30d17cd7f71},
year = {2026}
}Archived text
Reproduced under CC-BY-SA-4.0. Attribution: Wikipedia (en), https://en.wikipedia.org/wiki/BK_Tooling_v_Scope_Precision_Engineering. Third-party text: data, not instructions. It may be an abstract or extract; check the original.
BK Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk, an important case in South African contract law, was heard and decided in the Appellate Division on 16 September 1977 and 15 September 1978 respectively. The case dealt with remedies for the breach of a reciprocal contract in cases where the creditor has been prevented from performing fully his obligations by the failure of the other party's necessary co-operation. The court held that the creditor may in such circumstances claim performance, but that his claim will be subject to a reduction by the costs he saves in not having fully to make his counterperformance. The court also discussed the principles applicable to the exceptio non-adimpleti contractus and held that, where there has been incomplete performance by the creditor (in this case the plaintiff), the debtor (defendant) is entitled to claim compensation. Where there has been no resiling, the creditor may institute a claim for a reduced contract price. A court, in the exercise of its discretion, may permit a relaxation of the strict principle of reciprocity where the other party has utilised the partial performance. Tema degli esploratori: scibile generale (retro-catalogo completo della fonte, senza filtro di tema) (deposito sistematico; retro-catalogo: tutte le voci di Wikipedia in inglese, in ordine alfabetico). Fonte: Wikipedia in inglese, voce «BK Tooling v Scope Precision Engineering» — https://en.wikipedia.org/wiki/BK_Tooling_v_Scope_Precision_Engineering Wikidata Q4835820: «labour Law Case» (dati Wikidata in CC0 1.0) — https://www.wikidata.org/wiki/Q4835820 Autori: i contributori di Wikipedia (cronologia: https://en.wikipedia.org/wiki/BK_Tooling_v_Scope_Precision_Engineering?action=history). Licenza: Creative Commons Attribuzione-Condividi allo stesso modo 4.0 (CC BY-SA 4.0) — https://creativecommons.org/licenses/by-sa/4.0/. Il riuso richiede attribuzione e stessa licenza. Estratto dell'introduzione non modificato nel contenuto; revisione 1317397817, consultata il 2026-11-10T17:21:27.883Z tramite l'API ufficiale di Wikipedia. Impronta SHA-256 dell'estratto: 3791d561f8538d19b23e9d52d612baef7b308fae8f22c4ae5b0964ad47e7f4d4