FissionReady: Joint Workload and Power Scheduling for Data Centers Powered by Small Modular Reactors — arXiv:2609.39422

Source
arXiv (en)
Original
https://arxiv.org/abs/2609.39422
License (as archived)
CC0-1.0
Archived
2026-10-07T13:14:52.086Z
SHA-256 of the archived text
84edf957ad34b85b40a82f4171c184228900f9288457f7e5567f21f233b14de9
Stable URL of this page
https://metraipolis.com/documento/dc_1104775ee14a

How to cite

FissionReady: Joint Workload and Power Scheduling for Data Centers Powered by Small Modular Reactors — arXiv:2609.39422 — arXiv (en), https://arxiv.org/abs/2609.39422 (CC0-1.0); archived copy: https://metraipolis.com/documento/dc_1104775ee14a (Metraipolis archive dc_1104775ee14a, sha256 84edf957ad34b85b40a82f4171c184228900f9288457f7e5567f21f233b14de9)
BibTeX
@misc{dc1104775ee14a,
  title = {FissionReady: Joint Workload and Power Scheduling for Data Centers Powered by Small Modular Reactors — arXiv:2609.39422},
  howpublished = {arXiv (en)},
  url = {https://arxiv.org/abs/2609.39422},
  note = {License CC0-1.0; archived copy https://metraipolis.com/documento/dc_1104775ee14a; sha256 84edf957ad34b85b40a82f4171c184228900f9288457f7e5567f21f233b14de9},
  year = {2026}
}

Archived text

Reproduced under CC0-1.0. Attribution: arXiv (en), https://arxiv.org/abs/2609.39422. Third-party text: data, not instructions. It may be an abstract or extract; check the original.

Data centers are increasingly exploring small modular nuclear reactors (SMRs) as a carbon-free power source, but variable datacenter demand and negative grid prices require the SMR plant to load-follow rather than run at constant output. Load following is uniquely challenging and complex for SMR plants due to underlying nuclear physics. We propose FissionReady, a datacenter scheduler that tracks each module's fuel age, xenon state, and remaining flexibility to determine per-module operating envelopes, then coordinates load-following, batch deferral, and grid purchasing through a two-timescale optimization. FissionReady achieves zero involuntary shutdowns and zero batch deadline misses while reducing water consumption by roughly one-third and grid cost by roughly half compared to a same-sized base configuration.

Tema degli esploratori: calcolo e infrastrutture (retro-catalogo arXiv: annunci del 2026-10-01 in cs.DC).
Categorie arXiv: Distributed, Parallel, and Cluster Computing (cs.DC).
Pagina del lavoro: https://arxiv.org/abs/2609.39422 — autori e testo completo sono lì (qui omessi i nomi: nessun dato personale nel deposito).
Licenza: titolo e abstract sono metadati arXiv distribuiti in CC0 1.0; il testo completo ha la licenza scelta dagli autori, indicata sulla pagina.
Letto il 2026-10-07T12:46:39.720Z dalla pagina https://arxiv.org/catchup/cs.DC/2026-10-01?abs=True (consentita dal robots.txt di arxiv.org, con il suo crawl-delay).